fredy - 17 Nov 2006 21:08 GMT
I am just about finished digging out my barn floor.

I intend to lay gravel, sand, damp proof sheet, insulation (polystyrene),
about 4 inches of ready mixed concrete with steel work.

My question is at what level/order do I place the polystyrene insulation and
what are the benefits of its location.

Thanks for any info.

fred
Art  Yokell - 17 Nov 2006 22:03 GMT
Fred:

The polystyrene should be placed on top of the vapor barrier and the
concrete cast upon the insulation. The reason is that the purpose of the
vapor barrier is to prevent moisture from being forced into the insulation
under the pressure that is created by the temp. diff. Bring the vapor
barrier up the sides if possible and lap the joints by about 12-18". Your
reference to the damp proof sheet, I asssumed to be the vapor barrier. You
should try to use 10 mil Visqueen but at least 6 mil if you can't find the
10 mil.
>I am just about finished digging out my barn floor.
>
[quoted text clipped - 7 lines]
>
> fred
SteveF - 17 Nov 2006 23:01 GMT
>I am just about finished digging out my barn floor.
>
[quoted text clipped - 7 lines]
>
> fred

Vapor barrier under insulation.

Not all insulation board is rated for under slab use.  Check the
manufacturer's web site and make sure yours is.

Why are you putting down sand?

Steve.
Italian Mason - 21 Nov 2006 09:22 GMT
> Why are you putting down sand?

Sand should be put down under a vapor barior and on top of it
under to ensure the plastic is not torn on the jagged base and on top
so the concrete doesnt go off like a rocket while finishing it.

> >I am just about finished digging out my barn floor.
> >
[quoted text clipped - 16 lines]
>
> Steve.
Wayne Whitney - 21 Nov 2006 17:13 GMT
> Sand should be put down under a vapor barior and on top of it under
> to ensure the plastic is not torn on the jagged base and on top so
> the concrete doesnt go off like a rocket while finishing it.

By "go off like a rocket", I assume you mean set up really quickly.  I
thought that pouring conrete directly on a plastic vapor barrier
typically delays the setting up of the concrete, as there is nothing
to absorb the excess water used for placement.  The sand layer on top
of the vapor barrier would provide a more normal setting up time, as
it can absorb some of the excess water.  Have I got this backward?

Thanks, Wayne
Bob Morrison - 21 Nov 2006 17:31 GMT
In a previous post Wayne Whitney wrote...
> By "go off like a rocket", I assume you mean set up really quickly.  I
> thought that pouring conrete directly on a plastic vapor barrier
> typically delays the setting up of the concrete, as there is nothing
> to absorb the excess water used for placement.  The sand layer on top
> of the vapor barrier would provide a more normal setting up time, as
> it can absorb some of the excess water.  Have I got this backward?

No.  You got it right.  However, the tip about putting 2 layers of sand
with the vapor barrier between is a pretty good one.

BTW, ACI has issued new guidelines on using a plastic vapor barrier.
Basically, they are saying "DON'T USE ONE", unless you have a high ground
water problem and you have a flooring material that will have problems
with moisture (carpet, vinyl, wood).

In other words, try to take care of any moisture BEFORE it can migrate
through the slab.  This will be the case in most installations, so in most
cases a vapor barrier is not needed.

Signature

Bob Morrison, PE, SE
R L Morrison Engineering Co
Structural & Civil Engineering
Poulsbo WA
bob at rlmorrisonengr dot com

Stuart - 24 Nov 2006 15:14 GMT
> In a previous post Wayne Whitney wrote...
>> By "go off like a rocket", I assume you mean set up really quickly.  I
[quoted text clipped - 15 lines]
> through the slab.  This will be the case in most installations, so in most
> cases a vapor barrier is not needed.

I think Wayne may hose down the sand before pouring. Wayne and Bob, is that
a good idea?
Stuart//
Italian Mason - 26 Nov 2006 18:46 GMT
Sorry was out of town for a while..

No you are correct the sand layer on top does allow a more normal set
up time. The plastic accelerates the process greatly and on a hot day
concrete poured directly on plastic can damage the whole slab because
of the heat generation. To answer the question below (even though I was
not asked) yes you should spray down the sand or dirt or baserock or
whatever you are pouring over not wet wet but lightly moist.

> > Sand should be put down under a vapor barior and on top of it under
> > to ensure the plastic is not torn on the jagged base and on top so
[quoted text clipped - 8 lines]
>
> Thanks, Wayne
 
Sign In
Join
My Latest Posts
My Monitored Threads
My Blog
My Photo Gallery
My Profile
My Homepage

Start New Thread
Enable EMail Alerts
Rate this Thread



©2009 Advenet LLC   Privacy Policy - Terms of Use
This website includes both content owned or controlled by Advenet as well as content owned or controlled by third parties.